Drilling and Installation of Piping for Water Supply

During the months of February and March we had a drilling company from Quito drill and install the piping for our fresh water supply. The drilling depth was 90 meters which was exactly where our water studies indicated that our fresh water supply would be found. The next steps will be to install the water filtration plan and water tower that will supply the community with water.

water collage - 1

Taking Soil Samples 

During the months of February and March we had a soil testing firm from Portoviejo taking multiple soil samples in preparation of finalizing the design for the construction of the roads.

soil test

 

Installing Drainage Piping

 

drainage - 1

 

Road Construction In Progress

Road construction 1

 

Grading the Property