Instagram post by General Manager David Maksymuik from August 20 2019 through October 5 2019 of work being done at Las Olas. To continue to see current post as they happen go to Instagram and search for davidmaksymuik.

August 20

The clubhouse construction is coming along quickly. Right now all the walls are up and they are installing the plumbing and wiring into the wall panels. This will be followed by spraying the walls to complete the building to grey state.

August 20

House completed to grey state that is getting ready for inside finishes.

August 20

This house is waiting for the roof cement to dry before adding the final touches to bring it to grey state.

August 20

Installing roof beams on this house. Once complete the walls will go up and electrical will be installed. Followed by spraying the walls.

August 20

This picture shows eleven houses at Las Olas Ecuador in various stages construction at the current moment. Notice the Ceibo Valley golf course in the back ground.

August 26

Grading the location of the hillside condominiums continues this Monday morning.

August 26

Work continues on the Vista al Mar community retaining walls and four Row D houses.

August 26

Work continues to complete the first eight homes of Row A in the Vista al Mar community. Currently there are fifteen homes under construction and the clubhouse.

August 27

Spraying the first coat of cement on the clubhouse.


September 16

The clubhouse is being sprayed with cement and is quickly coming together.

September 17
The final corner of retaining wall E taking shape.

September 26

Digging the hole for the waste water treatment plant lift station. It is located by the 15th hole and pumps the grey water to the treatment plant.

September 26
The hole for the lift station incomplete. Next we pump the water out and build a concrete base for the lift station.

September 27

Working on installation of lift station for the waste water treatment process. The lift station pumps the waste to the treatment plant located by the equestrian center.

September 27
The power lines are currently being installed above ground to the back of the Vista al Mar community. From there they will travel will travel underground throughout the Vista al Mar and Las Playas communities.

September 27

The clubhouse is moving along nicely. All the walls are completed to grey state. Next up is the roof?

October 5

Multiple houses at various stages of construction with a view of the golf course and ocean in background.

October 5

The back nine holes at Ceibo Valley Golf Course are home to dunes on all but one hole. Shown here is a great example of the dunes on the par three 15th hole. What a great look it adds to the golf course.